Supply contract for 320 kV offshore HVDC system and 400 kV AC onshore cable
Total cable length
100 km onshore cable and 340 km offshore cable + 6 km onshore HVAC cable
Total cable route length
1,5 km onshore HVAC, 50 km onshore and 170 km offshore HVDC
Duration
2023-2027
Scope
The project
NKT contributes to one of the world´s largest offshore wind zones
We have now delivered the final HVDC onshore cable drum for the impressive Hornsea 3 Offshore Wind Farm. Thanks to the Ørsted Hornsea 3 project team for good collaborative working.