Contact
Find the right NKT contacts for your region here.
Ijmuiden kabel_trumma

Ijmuiden, the Netherlands

World´s first 525 kV XLPE HVDC submarine cable projects for offshore wind

Key facts

Client

TenneT

Location of the project

The Netherlands

Quantity of order

Turnkey 525 kV XLPE HVDC offshore and onshore cable system with a capacity of 2 GW

Total cable route length

Gamma: 147 km offshore and 8 km onshore Beta: 161 km offshore and 8 km onshore Nederwiek 2: 205 km offshore 0,4 km onshore

Total cable length

Beta: 147 km offshore and 8 km onshore Gamma: 161 km offshore and 8 km onshore Nederwiek 2: 205 km offshore 0,4 km onshore

Duration

Beta: 2023-2028 Gamma: 2023-2029 Nederwiek 2: 2023-2030
Ijmuiden lägger kabel i markfåra
Ijmuiden kabel_trumma

The project

The world´s first 525 kV XLPE HVDC offshore cable systems to connect 2 GW projects

Powercable 525 kV Maasvalakte outside Rotterdam
Here, the first cable pulling in Maasvlakte, Holland, was successfully completed.
Ijmuiden lägger kabel i markfåra
Loading...